JB Marks Service Delivery Update – Roads, Infrastructure & Community Milestone
- Karen Scheepers
- Sep 23
- 2 min read
The JB Marks Local Municipality has released its latest service delivery progress report, highlighting major road repairs, infrastructure support, and community milestones. The updates demonstrate the municipality’s ongoing efforts to improve critical infrastructure while celebrating the contributions of long-serving staff members.

Road Patching Success
Significant progress was achieved through the Road Patching Unit, with multiple priority routes completed:
Beyers Naudé Avenue – 100% Completion. All potholes were squared, stabilized, asphalted, and sealed. Work extended beyond the original scope to cover areas near the fuel station traffic lights.
Dr James Moroka & OR Tambo Intersection – 100% Completion. Repairs included squaring, stabilising, filling, and compacting the remaining side of the intersection, ensuring full restoration.
Additional Route Work. Proactive repairs were carried out at Tromonto Flats access road, MacArthur Potchefstroom Swimming Pool and Park area, and smaller potholes were addressed while teams were in transit.
Paving and Infrastructure Support
The paving team completed structural support work linked to electricity job cards, including paving and curb reinstatement. Concrete pouring was also finalised to ensure long-term stability and access for future maintenance.
Yellow Fleet Operations
Yellow Fleet teams supported ongoing projects by extracting G5 materials for the sewer project and stockpiling resources strategically at Mosidi Street, Ward 11. This groundwork provides essential support for long-term infrastructure reliability.
Celebrating Service – A Community Milestone
In addition to technical achievements, the municipality marked a special occasion: the 62nd birthday of Ntate Dire, a veteran of the Road & Stormwater Unit with 43 years of dedicated service since joining the municipality in 1982. His long-standing commitment was honored as a symbol of dedication and community spirit.
Impact Metrics
Three major road areas 100% completed
Multiple paving and infrastructure projects advanced
Strategic materials secured for sewer project support
Over 40 years of service celebrated through staff recognition
One legendary birthday milestone honored
Traffic Intelligence Strategy
The municipality reinforced its approach of working during low traffic periods to allow proper asphalt curing, prevent damage from heavy vehicles, enhance repair quality, and improve worker safety.
Community Notices
Beyers Naudé Avenue: Fully restored and open
Dr James Moroka & OR Tambo Intersection: Now 100% complete
Traffic Strategy: Residents thanked for cooperation during managed roadworks
Report Issues:
Water/Sewage: 082 381 0888
Roads/Paving: 018 293 1111
Disaster: 078 803 1570
Electricity: 082 385 1888

Moving Forward
Through the combination of road upgrades, infrastructure support, and recognition of dedicated staff, JB Marks continues to prioritise service delivery and community engagement. These initiatives highlight the municipality’s dual focus on improving infrastructure today while investing in sustainability and human capital for tomorrow.